Construction on the natural gas line along Wolfpit Road will continue this week as a crew works to install approximately 300 feet of pipe. They were to begin Monday, July 13, at 120 Wolfpit Road and work east toward Horseshoe Road. They expect to make it as far as 85 Wolfpit Road by Friday, July 17.
Construction takes place from 7 a.m. to 7 p.m., Monday through Friday. Access to homes and businesses will be kept open. The work is expected to continue through Aug. 154.