Quantcast
Channel: Wilton Bulletin – Wilton Bulletin
Viewing all articles
Browse latest Browse all 9137

Pipeline construction continues on Wolfpit Road

$
0
0

Crews work to install gas pipelines along Wolfpit Road. (Hayden Turek photo)

Crews work to install gas pipelines along Wolfpit Road. (Hayden Turek photo)

Construction on the natural gas line along Wolfpit Road will continue this week as a crew works to install approximately 300 feet of pipe. They were to begin Monday, July 13, at 120 Wolfpit Road and work east toward Horseshoe Road. They expect to make it as far as 85 Wolfpit Road by Friday, July 17.

Construction takes place from 7 a.m. to 7 p.m., Monday through Friday. Access to homes and businesses will be kept open. The work is expected to continue through Aug. 154.

Information: 860-665-4644 or GasExpansion@eversource.com.

More information is also available here.

The post Pipeline construction continues on Wolfpit Road appeared first on Wilton Bulletin.


Viewing all articles
Browse latest Browse all 9137

Trending Articles